1 60-2034—7RA890FFlame SafeguardPrimary ControlThe RA890F Protectorelay™ Primary Controlis a nonprogramming, amplifying relay that pro-vides solid sta
60-2034—7 10RA890FSERVICE • TROUBLESHOOTINGServiceGENERAL SERVICE1. Only qualified personnel should attempt to serviceheating equipment or controls.2.
11 60-2034—7RA890FTROUBLESHOOTINGterminal 6 with the controller calling for heat. If there ispower at terminal 6 and a line voltage controller is used
60-2034—7 12Home and Building Control Home and Building Control Helping You Control Your WorldHoneywell Inc. Honeywell Limited—Honeywell Limitée1985 D
60-2034—7 2RA890FSPECIFICATIONS • ORDERING INFORMATIONSpecif icationsTRADELINE® MODELSTRADELINE® models of this device are available. Theyare select
3 60-2034—7RA890FSPECIFICATIONSNOTE: Allowable inrush can be up to ten times the pilotduty rating.EXAMPLE: Pilot duty rating = 25 VA.At 120V, running
60-2034—7 4RA890FINSTALLATIONInstallationWHEN INSTALLING THIS PRODUCT…1. Read these instructions carefully. Failure to fol-low them could damage the p
5 60-2034—7RA890FINSTALLATIONIMPORTANT: Do not run high voltage ignition transformerwires in the same conduit with the flame detectorwiring.IMPORTANT:
60-2034—7 6RA890FINSTALLATIONFig. 4—Oil system with interrupted ignition.M875312345POWER SUPPLY. PROVIDE DISCONNECT MEANS AND OVERLOAD PROTECTION AS R
7 60-2034—7RA890FINSTALLATION • OPERATIONMOUNT RA890FDisconnect power supply.Remove relay cover (see Fig. 6) and position the RA890Fover the Q270A Sub
60-2034—7 8RA890FCHECKOUTCheckoutIF A STEADY READING OF AT LEAST MINIMUMSTRENGTH CANNOT BE OBTAINED, ONE OR MOREOF THE FOLLOWING CONDITIONS CAN EXIST:
9 60-2034—7RA890FCHECKOUTPILOT TURNDOWN TESTCAUTIONThe pilot turndown test should be performed onlyby qualified personnel and the instructions shouldb